Highlights of 2014 & 2015 Capital Projects

To ensure that our valued customers have power and “lights stay on”, Niagara Peninsula Energy Inc (NPEI) must replace or upgrade aging electrical equipment and install new equipment to ensure increased demand is met as our communities continue to grow and develop. Annually, NPEI sets out a capital budget to replace aged distribution system assets including poles, electrical hardware and underground systems. In addition to these capital projects, NPEI completes on-going maintenance on poles, switches, transformers, underground equipment, and tree trimming. NPEI is committed to delivering electricity with efficiency and reliability.

2014 Capital Projects Include:

  • 3M26, 3M28, 3M29 Underground Cable Replacements from Murray T.S. Niagara Falls
  • Overhead Distribution Plant Replacement and Relocation in Rolling Acres Subdivision Niagara Falls
  • King Street Overhead Line Extension Vineland
  • Overhead Line Rebuild and Voltage Conversion Brookfield Avenue, Barker Street, Clare Crescent, Niagara Falls
  • Overhead Line Reconstruction, Jordan Road between Red Maple and South Service Road Jordan
  • Crawford Street Overhead Line Reconstruction Niagara Falls
  • Replacement of End of Life Overhead Transformers West Lincoln Area
  • Municipal Substation Upgrades Pelham, Lincoln, West Lincoln, Niagara Falls
  • Line Upgrades on Portage Road, Bridgewater Street and Cummings Lane Chippawa
  • Overhead and Underground Line Reconstruction on Simcoe Street Niagara Falls
  • Overhead Pole Line Replacement and Voltage Conversion on Dorchester Road at Lundy's Lane, Niagara Falls
  • Circuit Switching Upgrades Overhead and Underground Lincoln, West Lincoln and Niagara Falls
  • Line relocations due to Municipal and Regional Road Improvements Pelham, Lincoln, West Lincoln and Niagara Falls
  • Pole Replacement Program Niagara Falls, Lincoln, West Lincoln
  • Distribution Betterments and New Customer Connections throughout the Service Territory
  • Kiosk Conversions Niagara Falls
  • New and Upgraded Revenue Metering Installations

 

2015 Capital Projects Include:

  • Overhead Distribution Line Relocation and Rebuild Beck Road North of Schisler Road Niagara Falls
  • King Street Overhead Line Extension  Vineland
  • Overhead Distribution Line Relocation and Rebuild Willodell Road South of Gonder Road Niagara Falls
  • Overhead Distribution Plant Replacement and Relocation in Rolling Acres Subdivision Niagara Falls
  • Overhead Line Reconstruction 8.32 kV loads off of  Jordan Municipal Station Lincoln
  • Overhead Line Rebuild and Voltage Conversion Brookfield Avenue, Garden Street, High Street Niagara Falls
  • Crawford Street Overhead Line Reconstruction Niagara Falls
  • Replacement of End of Life Overhead Transformers West Lincoln Area
  • Overhead Line Reconstruction on Willoughby Drive Chippawa
  • Overhead Pole Line Replacement and Voltage Conversion on Frederica DriveNiagara Falls
  • Circuit Switching Upgrades Overhead and Underground Lincoln, West Lincoln and Niagara Falls
  • Line relocations due to Municipal and Regional Road Improvements Pelham, Lincoln, West Lincoln & Niagara Falls
  • Pole Replacement Program Niagara Falls, Lincoln, West Lincoln
  • Distribution Betterments and New Customer Connections throughout the Service Territory
  • Kiosk Conversions Niagara Falls
  • New and Upgraded Revenue Metering Installations

 